Pji Bg Shape
Glenroy Station
7glenroy 1

Glenroy Station

Date Completed: December 2020 to April 2022
Budget: $250/$300 million
Contractor: John Holland
Location: Melbourne, Victoria
The Glenroy Station project involved the removal of the level crossing and lowering the rail line underground. The client has managed this project over a two-year period which also includes a new Glenroy Station. It was a 14-metre-deep cut (with a distance of 1.2km underground) which Stilcon Scaffolding provided drop access scaffold into the cut and bridge structure access scaffolds across the cut.
308 Exhibition Street, Tower 2
308exhibitionst

308 Exhibition Street, Tower 2

Date Completed: December 2022 to April 2023
Budget: $10 million
Contractor: Multiplex
Location: Melbourne, Victoria
The 308 Exhibition Street project required our team to create a solution for working on an almost finished building. Our team had to create a solution to access without tying into the building. Usually large, weighted beams at this height are specifically for a building demolition - where there is  minimal concern for preserving the building's integrity. At 308 Exhibition Street Tower 2, there were four engineered heavy-duty trusses, which were fabricated in-house at our facility. Our team designed square hollow round section trusses, which were bolted and fabricated at approximately 15 metres in length. The trusses varied in width from 1.2 metres to 2.4 metres and in height from 1.5 metres to 1.8 metres and weighed 7 - 8 tonne.
308 Exhibition Street, Tower 1
Dji 0995

308 Exhibition Street, Tower 1

Date Completed: October 2022 to April 2023
Budget: $10 million
Contractor: Multiplex
Location: Melbourne, Victoria
The project at 308 Exhibition Street, needed our team to create a solution to work on a basically finished building for the client to finish off the GRC panelling. Using our teams’ depth of experience enabled us to design and engineer trusses to fit into the unfinished Level 11, with scaffolding being built on the truss and tied back into the building. We designed square hollow round section trusses bolted and fabricated at approximately 15 metres long. The trusses ranged in width from 1.2 metres to 2.4 metres and in height from 1.5metres to 1.8 metres. The trusses was engineered, fabricated, and painted at our facility and then transported to site.
Glenroy Station Pedestrian Bridge

Glenroy Station Pedestrian Bridge

Date Completed: December 2020 to April 2022
Budget: $250/$300 million
Contractor: John Holland
Location: Melbourne, Victoria
This project required the supply of a Layher scaffold pedestrian bridge spanning 18 metres from one side of the platform to the other. The Stilcon Scaffolding entire team worked together to create an innovation solution to developing this bridge as this had not been done before on any level crossing project to date, in the southern hemishpere. The DDA & BCC compliant Layher scaffold pedestrian bridge had two stretch stairs adjoined either side of the 18 metre span.
Coburg & Moreland Station
Coburgmoreland Featured

Coburg & Moreland Station

Date Completed: 2020 to 2021
Budget: $600 million
Contractor: John Holland (NWPA)
Location: Melbourne, Victoria
Stilcon Scaffolding was engaged, by John Holland to work with them on the 2km Skyrail project. This project involved the removal of two level crossings between Moreland and Coburg stations respectively. The $600 million project was scheduled to be the largest occupation of the southern hemisphere with a program to complete over 90 days. In an unprecedented event the project was completed 30 days ahead of schedule.
Hallam Station
Hallam Banner (1)

Hallam Station

Date Completed: September 2021 – April 2022
Budget: $300 million
Contractor: Laing O’Rourke
Location: Melbourne, Victoria
The Hallam Road project determined that the best way to remove the level crossing was to build a rail bridge over Hallam Road. Stilcon Scaffolding were engaged to supply structure access onto and into the u trough as well as edge protection. Stilcon Scaffolding design and engineering team were to supply design which ensured all safety elements and logistics required for the duration of the project were meet. The team needed to fulfil all egress and aggress for all workers on a 14-metre high skyrail with one station.
West Gate Bridge Painting Project – Pier 15
Bannerdji 0166 1

West Gate Bridge Painting Project – Pier 15

Date Completed: December 2021 – June 2022
Budget: $70 million
Contractor: CPB Contractors
Location: West Gate Bridge – Pier 15 
The West Gate Bridge is a steel, box girder, cable-stayed bridge in Melbourne, Victoria spanning the Yarra River just north of its mouth into Port Phillip. It carries the West Gate Freeway and is a vital link between Melbourne CBD and the western suburbs. The high span bridge was built to allow large cargo ships to access the docks in the Yarra River. It is one of the highest road decks in Australia, clearing the water at 58 metres and has a total length of 2.58km.
West Gate Bridge Painting Project – Pier 10
Wgb Banneroption2 1

West Gate Bridge Painting Project – Pier 10

Date Completed: December 2021 - ongoing
Budget: $70 million
Contractor: CPB Contractors
Location: West Gate Bridge – Pier 10
The West Gate Bridge has a long history with building commencing in 1968. Two years into construction of the bridge, at 11.50 am on 15 October 1970, the 112m (367.5 ft) span between piers 10 and 11 collapsed and fell 50m (164 ft) to the ground and water below. Thirty-five construction workers were killed. A monument has been erected at the base of Pier 10 to the fallen workers. This created a unique environment for the team to work in as they were building around this monument – even with the much advance knowledge, vision and engineering the team now has and the capabilities of the team – they are still aware of the danger and the history of that bridge and ensured at all time safety was of extreme importance to everyone.
Parkville Station
Banner 1

Parkville Station

Date Completed: March 2021 - ongoing
Budget:
Contractor: Cross Yarra Partnerships
Location: Melbourne, Victoria
Parkville Station will be on the doorstep of Victoria’s world-renowned education, health and research precinct. The Metro Tunnel will enhance access to The University of Melbourne and facilities such as The Royal Melbourne Hospital, The Royal Women’s Hospital and Peter MacCallum Cancer Centre. The new Parkville Station will provide a direct train connection to the area for the first time and relieve pressure on local trams and roads. 
Mentone & Cheltenham Station
Banner

Mentone & Cheltenham Station

Date Completed: December 2019 – November 2021
Budget: $500 million
Contractor: SPA ( Southern Project Alliance), Lendlease Engineering & Acciona
Location: Melbourne, Victoria 
The Mentone & Cheltenham Station level crossing removal required a 14-metre cut into sand belt land. Stilcon Scaffolding assisted with the restoration of the two heritage listed stations. The design and engineering team designed compliant layher stretcher stairs that could be craned into position and incorporated with the cut of the 14 metres. The stairs were built in four metre sections and the cut was 4 metres below the road level. Stilcon Scaffolding provided bridge scaffold from one side of the cut to the other, spanning approximately 18 metres.
Werribee & Hoppers Station
Wepa Banner (1)

Werribee & Hoppers Station

Date Completed: March 2020– March 2022
Budget: $600 million
Contractor: McConnell Dowell
Location: Melbourne, Victoria 
Stilcon Scaffolding was engaged to work on the Werribee Station & Hoppers Crossing Station level crossing removal in the over road project. The team designed scaffolds to egress and access, as well as safe protection of u troughs of the over road/rails project which spanned from Werribee to Hoppers Crossing. Stilcon Scaffolding supplied riggers for safe access and rescue procedures in the lift shafts for both projects.
Chisholm Road Prison
Chisholm Road Prison

Chisholm Road Prison

Date Completed: February 2020 – February 2022
Budget: $1.8 billion 
Contractor: John Holland
Location: Chisholm Road Prison
Chisholm Road Prison is a new maximum-security prison being built in the vicinity of the Lara prison precinct, which will accommodate 1,248 prisoners when finished. With a focus on community safety, the state-of-the-art facility will feature the highest and most stringent level of security.
Melbourne International Airport
Banner Melbourneairjpg

Melbourne International Airport

Date Completed: February 2020 – July 2020
Budget: $10 million
Contractor: Maz Group
Location: Melbourne, Victoria
The client needed to remove all fire flammable cladding off the terminal building and the connecting hotel. The flammable cladding was all the way from the passenger side to the operational side of the airport. It was imperative to ensure the ongoing operation of the airport was not compromised during the life of the project.
Queen Victoria Market Precinct Renewal
Img 8417 2 1

Queen Victoria Market Precinct Renewal

Date Completed: December 2020 – April 2022
Budget: $450 million
Contractor: Mirvac
Location: Melbourne, Victoria
Mirvac and Melbourne-based PDG entered into an agreement to develop the $333.5m build-to-rent project of 490 residences last year. The project sits alongside the $250 million Queen Victoria Market precinct renewal. Stilcon Scaffolding was engaged to provide the perimeter scaffolding and encapsulation for the structures team and finishing teams to work on.
East Brunswick Village
Eastbrunswick4 Bnw

East Brunswick Village

Date Completed: January 2018 – December 2020
Budget: $200 million
Contractor: Hacer
Location: Melbourne, Victoria
Stilcon Scaffolding provided a perimeter scaffolding 25 to 30 metres high with full wrap to create protection while the building was in construction. The team provided survey points to build the scaffold for the one build but two process build where the structures team and the finishing trades could work together. The encapsulation also helped reduce falling hazards.
77 River Street South Yarra 
77 River Banner

77 River Street South Yarra 

Date Completed: October 2021 – January 2022
Budget: $400,000
Contractor: MAZ Group
Location: Melbourne, Victoria
The establishment of Cladding Safety Victoria by the Victorian Government is a world-leading initiative. The Victorian Government is committed to a building system that delivers safe, quality buildings and so has developed a comprehensive cladding rectification strategy to reduce the fire and safety risks of private residential buildings to an acceptable and tolerable level.
Brunswick Brickworks
Dsc02000

Brunswick Brickworks

Date Completed: December 4, 2021 – ongoing
Budget: $450 million
Contractor: Glenvill Developments
Location: Melbourne, Victoria
Stilcon Scaffolding was engaged to supply 35 metre high scaffold around the circumference of the heritage listed chimney at Hoffman Brickworks so as to enable the inspect of the brickwork. Once this inspection was completed the scaffold enable the repair and maintenance of the damage and decay caused by age to the brickwork chimney.
Logo
Stilcon 1 White

Stilcon Scaffolding now Stilcon Industrial Services

Stilcon Industrial Services

Share This

Select your desired option below to share a direct link to this page.
Your friends or family will thank you later.